ALL PROJECTS
	(Updated 5 Dec 2009)
	
		- Construction of 2000 living units & service buildings
- Upgrade Tagriffet Control Building
- Concreting works for Nalut Flow Control Station (NFCS) Regulating Tank
- Construction of Reservoir Tanks at Gharyan Water Supply Project
- Concreting Works of Pumping Stations 1 and 2
- Concreting Works of Pumping Stations 3 and 4
- Technical Services to Al-Nahr Company Ltd
- Construction of Maintenance workshop at Samah Oilfields for Waha Oil 
		Company
- Construction of Al-Juawaibiyah Regulating Tank at Nalut
- Oilfield Services at Ghani Oilfields
- Oilfield Services at Amal Oilfields
- Technical Services to LISCO
- Construction of Green Printing Press Complex
- Construction of Pump Stations & Turnout Headworks
- Construction of Accomodation Blocks
- Construction of Heavy Equipment Workshop
- Construction of 177 Farm Tanks
- Construction and repair of Amal Airport
Please Scroll down for project descriptions & status
	
		
			
			Upgrade Tagriffet Control Building
			
				
				
					
					
						VEBA Oil Operations. (Petro Canada)
					 
				 
				
				
				
				
					
					
						The project comprises of construction of a new control 
						room building with steel portal frame, block walls and sandwich 
						panel roof. The work also includes design and installation 
						of HVAC system, telephone, electrical, general and emergency 
						lighting, sanitary and waste water system, potable water 
						system, fire water, fire fighting and fire alarm systems. 
						Work is in progress as per approved schedule.
					 
				 
			 
			
		 
		
			
			Concreting works for Nalut Flow Control Station (NFCS) Regulating 
			Tank
			
				
				
					
					
						Al Nahr Company (Fully owned by Great Man-made River 
						Authority)
					 
				 
				
				
				
					
					
						Nalut, Gadames-Zwara-Al Zawiah Water System for Great 
						Man-Made River project, Libya
					 
				 
				
				
					
					
						The work comprises of civil construction of 70,000 cubic 
						meter capacity regulating tank with specialized formwork 
						for columns, walls and roof panels. The work involved about 
						12678 cubic meters of concrete work and 2100 tons of rebar 
						fabrication and installation. Work is in progress and is 
						expected to be completed ahead of schedule.
					 
				 
			 
			
		 
		
			
			Construction of Reservoir Tanks at Gharyan Water Supply Project
			
				
				
					
					
						Al Nahr Company (Fully owned by Great Man-made River 
						Authority)
					 
				 
				
				
				
					
					
						Gharyan Water Supply Project PH-2, Gharyan, Libya
					 
				 
				
				
					
					
						The work comprises of civil construction of 4 No. reservoir 
						tanks with capacities ranging from 1000 to 3000 cubic meter 
						with specialized formwork for columns, walls and roof panels. 
						The work involved about 3091 cubic meters of concrete work 
						and 500 tons of rebar fabrication and installation. Work 
						is in progress as per approved schedule.
					 
				 
			 
			
		 
		
			
			Concreting Works of Pumping Stations 1 and 2
			
				
				
					
					
						Al Nahr Company (Fully owned by Great Man-made River 
						Authority)
					 
				 
				
				
				
					
					
						Gadames, Gadames-Zwara-Al Zawiah Water System for Great 
						Man-Made River project, Libya
					 
				 
				
				
					
					
						The work comprises of civil construction of two 20,000 
						cubic meter capacity forebay tanks, two pumping stations 
						with electrical buildings, chlorination buildings, feeder 
						tanks, shafts and other appurtenant structures. The work 
						involved about 16738 cubic meters of concrete work and 2500 
						tons of rebar fabrication and installation. Both forebay 
						tanks and pumping stations with electrical buildings have 
						been completed ahead of approved schedule. Work on the remaining 
						appurtenant structures is progressing as per approved schedule.
					 
				 
			 
			
		 
		
			
			Construction of 2000 living units and service buildings
			
				
				
					
					
						Housing Infrastructure Board, Tripoli, Libya.
					 
				 
				
				
				
				
					
					
						The original project comprised of development of a master 
						plan over an area of 102 hectares along with design and 
						construction of 2000 living units and associated public 
						buildings near the city of Alkhoms, district Almarqab. However 
						on 26 November 2008 the scope of development of master plan 
						increased from 102 hectares to 237 hectares and as per changed 
						requirements a new master plan accommodating 3450 units 
						and associated public buildings has been prepared and submitted. 
						In addition to the housing units urban plan includes service 
						buildings, public buildings, parks and roads. Utilities 
						like water, power and sewerage for the development project 
						are integrated with the regional infrastructure.
						Mobilization has been completed at site and client approval 
						for buildings and master plan is awaited to commence work. 
						The work is expected to be completed within the stipulated 
						construction period of 27 month after receipt of design 
						approval and site hand over.
					 
				 
			 
			
		 
		
			
			Concreting Works of Pumping Stations 3 and 4
			
				
				
					
					
						Al Nahr Company (Fully owned by Great Man-made River 
						Authority)
					 
				 
				
				
				
					
					
						Aljuwaibiyah, Gadames-Zwara-Al Zawiah Water System for 
						Great Man-Made River project, Libya
					 
				 
				
				
					
					
						The work comprises of civil construction of one 20,000 
						cubic meter capacity forebay tank, two pumping stations 
						with electrical buildings, chlorination buildings, feeder 
						tanks and other appurtenant structures. The work involved 
						about 11333 cubic meters of concrete work and 1900 tons 
						of rebar fabrication and installation. Work on the last 
						pumping station is in progress as per approved schedule. 
						All the remaining works have been completed ahead of schedule.
					 
				 
			 
			
		 
		
		
			
			Construction of Maintenance workshop at Samah Oilfields for Waha 
			Oil Company
			
				
				
					
					
						Industrial Engineering Company
					 
				 
				
				
				
				
					
					
						The scope of work comprised of design and construction 
						of a workshop for welding, AC repair and equipment maintenance 
						with covered area of 3000 sqm. The steel structure consists 
						of 8m high and 20m span portal frames with provision of 
						two gantry cranes of 5 and 10 tons. A mezzanine floor with 
						composite roof construction provides space for storage, 
						facilities and offices. Being a fast track project, design 
						along with procurement of off shore materials was completed 
						well ahead of construction schedule. Further activities 
						are on hold due to client pending contractual obligations.
					 
				 
			 
			
		 
		Construction of Al-Juawaibiyah Regulating Tank at Nalut
		
			
			
				
				
					Al Nahr Company (Fully owned by Great Man-made River Authority)
				 
			 
			
			
			
				
				
					Aljuwaibiyah, Gadames-Zwara-Al Zawiah Water System for Great 
					Man-Made River project, Libya
				 
			 
			
			
				
				
					The work comprises of civil construction of 70,000 cubic 
					meter capacity regulating tank with specialized formwork for 
					columns, walls and roof panels. The work involved about 11850 
					cubic meters of concrete work and 2000 tons of rebar fabrication 
					and installation. Work has been completed as per approved construction 
					schedule.
				 
			 
		 
		
	 
	
		
		Oilfield Services at Ghani Oilfields for Harouge Oil Operations
		
			
			
				
				
					Electro-mechanical, mechanical, electrical and civil works 
					at various stations at Ghani oilfields as follows; a. Preventive 
					maintenance of Storage Tanks ST 222, ST 401, ST 701 and St 201 
					at Ghani & Zenad Stations.
				 
			 
		 
		
	 
	
		
		Oilfield Services at Amal Oilfields
		
			
			
			
				
				
					Preventive maintenance of Storage Tanks and Pipe Lines at 
					various stations in Amal Oilfields as follows; a. Surge Tank, 
					Settling Tank, and Gas Boot at Station 3 b. Surge Tank, Settling 
					Tank, and Gas Boot at Station 7
				 
			 
		 
		
	 
	
	
	
		
		Construction of 2 Pump Stations and 3 Turnout Head Works
		
			
			
				
				
					Al-Nahr Company (fully owned by The Great man-made River 
					Authority)
				 
			 
			
			
			
			
			
				
				
					Pump Stations with an average area of 5,000 sq meters 6 meter 
					deep. The 3 Turn out Head works are 3 meter deep below grade 
					reinforced concrete structures with a control room on the ground 
					floor. The project required approximately 5000 cubic meters 
					of cast in place concrete and approximately 600 Tons of Steel 
					reinforcements
				 
			 
		 
		
	 
	
	
		
		Construction of Heavy Equipment Workshop
		
			
			
				
				
					Veba Oil Operations. (Petro Canada)
				 
			 
			
			
			
			
				
				
					The project comprises of a 7.5m eaves height steel structure 
					building with 22m span and two overhead cranes. The lean to 
					section comprises of engine repair workshops, stores, kitchens, 
					washrooms and offices. The facility is equipped with oil dispensers, 
					tyre repair facilities, compressed air network, vacuum suction 
					network, fire alarm systems, smoke alarm systems and fire fighting 
					facilities.
				 
			 
		 
		
	 
	
	
		
		Construction of North Accommodation Blocks
		
			
			
			
			
			
			
				
				
					The scope of work comprised of design and construction of 
					five new accommodation blocks at AMAL oil field. In addition 
					to the structural design and construction of buildings, the 
					work also included design and installation of HVAC system, telephone, 
					electrical, general and emergency lighting, sanitary and waste 
					water system, potable water system, fire water, fire fighting 
					and fire alarm systems.
				 
			 
		 
		
	 
	
		
		Provision of Technical Services to Libyan Iron & Steel Company
		
			
			
			
				
				
					Provision of highly skilled Engineers, Specialists, Plant 
					Operators and Technicians in the Operations Deptt, Maintenance 
					Deptt, Direct Reduction Plant and the Flat Mill.
				 
			 
		 
		
	 
	
	
		
		Construction of 177 Farm tanks at Tarhuna
		
			
			
				
				
					Al-Nahr Company Limited (Fully owned by The Great Man-Made 
					River Authority)
				 
			 
			
			
			
			
				
				
					The project comprises construction of 177 farm tanks for 
					the water supply and irrigation network. The tanks are made 
					of reinforced concrete, 300mm thick walls and are cast in place 
					at various locations along the network.
				 
			 
		 
		
	 
	
		
		Construction and repair of Amal Airport
		
			
			
				
				
					Veba Oil Operations. (Petro Canada)
				 
			 
			
			
			
			
				
				
					The project comprises construction and repair of an airport 
					at Amal oilfields. Modifications were also done to the Aviation 
					Fuel system. The repair work included rehabilitation of the 
					existing runway strip, 7000 meters of crack widening, routing 
					and filling with specially designed sealant, milling and dispensing 
					machines for extreme climates.
				 
			 
		 
		
	 
	
			
			Provision of Technical Services to Al-Nahr Company Ltd.
			
				
				
					
					
						Al Nahr Company (Fully owned by Great Man-made River 
						Authority)
					 
				 
				
				
				
				
					
					
						Provision of highly skilled Engineers, Specialists, Plant 
						Operators & Technicians in the Operations, Transportation, 
						Manufacturing departments of the worlds biggest Prestressed 
						Concrete Pipes (PCCP) Fabrication Plant.
					 
				 
			 
			
		 
		
		
		Construction of Green Printing Press Complex
		
			
			
				
				
					Libyan Investment Company, Tripoli, Libya.
				 
			 
			
			
			
				
				
					Sawani Road Tripoli, Libya
				 
			 
			
			
				
				
					Project Area 26,500 sq meters Portal frame building 6,300 
					sq meters Admn Building 1,680 sq meters Expert & workers 
					residence, Warehouse, services building, compressor room, overhead & 
					underground fire water tank, electrical control room, internal 
					roads, water supply & sewage network, boundary wall.